Construction Update

Here's the progress Monarch made this past week on OHP's Building Construction and Renovation project: 

New Addition: 

  • Exterior perimeter CFMF wall framing
  • 1st floor light gage metal framing
  • 2nd floor interior light gage metal framing (layout)
  • Roof steel detailing, including framed openings


Interior Work: 

  • Demolition and renovation continues in the old building for new offices. 
  • Water lines continue to run through the corridors

New Mechanical Room: 

  • New electrical switch gear being installed in the new mechanical area
  • New air handler being installed in new lab areas