It was an exciting week as preparations are being done to tear down the old Adult Education and storage warehouse buildings to allow for better access to OHP's front entrance. 

OHP's will utilize other buildings on campus for storage and Clark State will utilize existing buildings near the front of campus for adult education offerings. 

Here's the progress Monarch Construction has made this week: 

New Addition: 

  • Concrete pouring on the second floor. 
  • Roof joist and decking erection.

Diesel Addition: 

  • Delivery and installation of miscellaneous air handlers and HVAC exhaust fans
  • Polished floors. 
  • Painted walls. 
  • Worked on electrical panels and wiring. 

New Mechanical Room: 

  • Gas piping connected to boilers
  • Corridors steel framing for pipe support install
  • Sprinkler piping through rooms

Interior Renovations: 

  • Demolition of 102A meeting room. 
  • New door access in 600 hallway. 


New Roof: 

  • Continued roofing work. 

Additional Site Work: 

  • Asphalt patch water main in Student Parking Lot
  • Water main dig, prep, install and backfill East perimeter of site
  • Water main dig, prep, install, inspect and backfill South of site