It was an exciting week are the building addition is starting to take form! The new building addition  will house the new Cosmetology and Culinary Arts programs as well as Health Careers Academy and Education Academy. The new science labs will also be located in the new addition. 

Addition: 

  • Setting steel structure for building addition
  • Continued work on elevator shaft 

Interior Work: 

  • Monarch is preparing to pour the foundation for the Diesel expansion. 
  • Restroom and classroom demolition has begun. 
  • A new roof is being installed above the Automotive labs.