Search Site

This search form uses an instant search feature. As you type, search results will appear automatically below the search field. When you've entered you desired search terms use tab to navigate through the available results and hit enter to open the selected page or document.
Construction Update: Week of  May 6
Construction Update: Week of May 6
Kelsey Webb
Wednesday, June 02, 2021

As renovations continue on campus, we were excited to re-home our lockers to Indian Lake Schools and Triad High School! Indian Lake Administration was on campus to assist with the removal of their lockers. In addition, our gently used chiller/AC unit was donated to Fairborn High School as we prepare our new mechanical room for a bigger chiller/AC unit to meet the needs of the expanded high school building.

Monarch Construction continued work on the renovation project this week including: 

Addition: 

  • Preparing another concrete pour 

Interior Renovations: 

  • The Welding and Fabrication lab is undergoing renovations, including a room for storage and a separate classroom that isn't placed within the lab space. 
  • Works continues in the Outdoor Careers area. 

New Mechanical Room: 

  • Work continues in the new mechanical room, preparing for new equipment and the new chiller/AC unit.