Monarch Construction worked on the following this week: 

New Building Wing

  • Block wall construction has begun
  • Underground sewage lines continue to be installed

Site Work

  • Removed existing cooling towers to prepare for new ones to be installed 
  • A temporary pedestrian walkway was put in to easily walk around the construction site between the administrative building and high school building.